FG ADDS 272MW TO LAGOS GRID AS TEGBE COMMISSIONS UPGRADED ALAUSA, LEKKI SUBSTATIONS
New Transformers To Boost Power For Ikeja, Lekki, Victoria Island And Surrounding Business Hubs
The Federal Government on Tuesday commissioned upgraded transmission infrastructure in Alausa and Lekki, injecting a combined 272MW of bulk power into Lagos and easing decades-old constraints in the state’s busiest economic corridors.
Written By Dedeigbo Samson Ayodeji
Posted By Town Crier News Nigeria
Published By Fitness Network Communications
Minister of Power, Joseph Tegbe said the upgrades are part of President Bola Tinubu’s push to “confront the infrastructure constraints that have limited Nigeria’s economic potential.
WHAT THE UPGRADES DELIVER
1. Alausa Substation: An old 30MVA transformer was replaced with a new 100MVA unit.
Station capacity rose from 135MVA to 205MVA, adding 80MW for Ikeja Electricity Distribution Company, IKEDC.
2. Lekki Substation: TCN installed 2x60MVA, 132/33kV transformers and 9 new 33kV feeders.
132/33kV capacity doubled from 120MVA to 240MVA, adding about 192MW for Eko Electricity Distribution Company, EKEDC.
The Lekki project, handled by Shanghai Electric Group with World Bank support, will also include an additional 1x300MVA, 330/132kV transformer scheduled for energisation in November 2026.
“IDENTIFY THE BOTTLENECK. REMOVE THE CONSTRAINT”
Speaking at both commissioning events, Tegbe said the projects reflect government’s deliberate strategy to fix structural bottlenecks in the power sector.
“Identify the bottleneck. Invest in it.
Remove the constraint. Unlock the capacity,” he said, adding that ageing equipment and stranded power would continue to be addressed nationwide.
He commended TCN, NISO, EKEDC, IKEDC, Shanghai Electric and the World Bank for delivering the projects, and congratulated Governor Babajide Sanwo-Olu for sustaining an enabling environment for infrastructure investment in Lagos.
TCN: MORE STABLE POWER FOR 70,000+ RESIDENTS
Engr. Sule Ahmed Abdulaziz, MD/CEO of TCN, said the Alausa upgrade, also executed by Shanghai Electric under World Bank funding, will provide more stable and reliable electricity to at least 70,000 residents through IKEDC upon energisation.
He described the projects as proof that “TCN remains resolute in its mandate of building and sustaining a robust transmission network, capable of transporting Nigeria’s growing power needs to various distribution load centres nationwide.”
Abdulaziz noted the upgrades will strengthen grid stability and enable more bulk power to reach DisCos for onward supply within their franchise areas.
Speaking the truth... | Town Crier News Nigeria | Whatsapp No: 08027723347, 08072777599,08122784467,09063474539